- Clear regulations state that construction contracts may be revised even during the extended terms.
- As for unit price contracts, contractual unit prices will be adjusted if:
+ The State changes policies, directly affecting the performance of the contract, unless the contracting parties agree otherwise;
+ The revised project affects the contract, unless the contracting parties agree otherwise;
+ Any force majeure event prescribed by laws occurs.
- Lump-sum contracts will be adjusted if:
+ The State changes policies, directly affecting the performance of the contract, unless the contracting parties agree otherwise;
+ The revised project affects the contract, unless the contracting parties agree otherwise.
See more details in clause 12, Article 1 of the Decree No. 50/2021/ND-CP (in force as of April 1, 2021).