On February 15, 2017, the Ministry of Construction promulgated the Decision No. 79/QD-BXD on the cost norms for project management and construction investment consultancy.

As of March 01, 2017, the following cost norms newly defined in the Decision No. 79 shall take effect, for example, against a project whose total cost of construction and equipment (excluding VAT) is VND 10 billion or less:

- Management cost norm for civil construction is 3.282%;

- Management cost norm for industrial construction is 3.453%;

 - Management cost norm for transport construction is 2.936%;

- Management cost norm for agricultural and rural development is 3.108%;

- Management cost norm for technical infrastructure is 2.763%.

Decision No. 79/QD-BXD comes into force as of March 01, 2017 and replaces the 2009's Decision No. 957/QD-BXD .

2.188

More headlines

Most Viewed

Address: 17 Nguyen Gia Thieu street, Ward Vo Thi Sau, District 3, Ho Chi Minh City, Vietnam.
Phone: (+84)28 3930 3279 (06 lines)
Email: info@ThuVienPhapLuat.vn

Copyright© 2019 by THƯ VIỆN PHÁP LUẬT
Editorial Director: Mr. Bui Tuong Vu

DMCA.com Protection Status